CONSTRUCTION PROGRESS

Date: 30th April 2021
 
Structural work has now almost completed on the two side blocks, with one side already seeing bricking started and the other having the final ceiling added before the bricking and plastering commences.  
 
The plastering, plumbing and bricking continues in the inner structures of the side and back blocks and the bathroom tiling and first paint coat and plastering conitinues in the front block, alomg with work in the communal hall and stairways.
 
This month you can really see the bathroom wall and floor tiles taking shape, the tiles have been upgraded to give a modern and quality finish.
 